Vizsla delays first silver at Panuco by a year
Vizsla Silver has delayed first production at its Panuco silver-gold project in Sinaloa, Mexico by one year to the second half of 2028, following the abduction and killing of 10 workers in January 2026. Engineering is approximately 50% complete and 85% of processing plant equipment has been ordered, but key federal environmental and land-use permits remain outstanding and no construction decision has been made. The November 2025 feasibility study, which projected US$238.7 million initial capital and 94.7 million oz payable silver over 9.4 years, has not been updated to reflect the revised schedule or potential cost escalation.