MEK: Ore Sorter Commissioning Delivers 5X Grade Increase
Original announcement by asx on
- Company
- Meeka Metals Limited
- Ticker
- MEK
- Exchange
- ASX
- Region
- Western Australia
- Primary commodity
- Unavailable
- Secondary commodities
- None reported
- Document categories
- Metallurgy
- Extracted
- 2026-11-17 22:24:49 UTC
Analysis by Minestarters Atlas
Atlas analysis published:
Minestarters Atlas analysis
Summary
Meeka Metals has successfully commissioned a Steinert multi-sensor ore sorter at the Murchison Gold Project. The sorter has achieved a five-fold grade increase, producing a 4.39 g/t Au product from a 0.86 g/t Au feed while recovering 80-90% of the gold.
Reasoning: The commissioning of the ore sorter successfully demonstrated a 5x grade increase for the product stream, significantly improving the feed grade to the mill.
Positive factors
- Significant grade upgrade from 0.86 g/t to 4.39 g/t Au
- High gold recovery (80-90%) into a small mass fraction (16%)
- Successful commissioning of new technology
- Reliable throughput of 60 tph
Negative factors
- Results are based on a relatively small sample size (5,412t)
Facts used in scoring: 3

Classification and evidence
Mill Routeneutral
Processing via mill or concentrator (CIL, CIP, tank leach, flotation).
Why it applies: The ore sorter product is processed through the mill.
Evidence · text
“Product is processed through the mill”
Multi-Domain Testedpositive
Variability across ore domains (oxide, transition, fresh) has been addressed.
Why it applies: 3 distinct composites were tested
Extracted facts
Stored fact records: 3. Some facts used in scoring do not have a stored record.
Metallurgical Results (3)
ore sorterMurchison Gold Project · goldHead Grade: 0.97Head Grade Unit: g/tView all detailsHide details
Identity
- Project
- Murchison Gold Project
- Commodity
- gold
- Region
- australia_wa
- Reported Region
- Western Australia
- Ticker
- MEK
Test Work
- Program Status
- optimization
- Test Type
- ore sorter
- Processing Route
- ore sorter
- Sample
- High Grade setting product
Recovery
- Head Grade
- 0.97
- Head Grade Unit
- g/t
- Conc. Grade
- 4.31
- Conc. Grade Unit
- g/t
- Tailings Grade
- 0.19
- Tailings Grade Unit
- g/t
Lab
- Laboratory
- Meeka’s site laboratory
Review
- Needs Review
- No
- Historical
- No
Dates
- Event date
- 2026-11-17T00:00:00.000Z
Reasoning: Successful high-grade setting performance.
Positive factors
- High grade product achieved
Evidence · table
“4.31”
Context: 1,324
ore sorterMurchison Gold Project · goldHead Grade: 0.83Head Grade Unit: g/tView all detailsHide details
Identity
- Project
- Murchison Gold Project
- Commodity
- gold
- Region
- australia_wa
- Reported Region
- Western Australia
- Ticker
- MEK
Test Work
- Program Status
- optimization
- Test Type
- ore sorter
- Processing Route
- ore sorter
- Sample
- Balanced setting product
Recovery
- Head Grade
- 0.83
- Head Grade Unit
- g/t
- Conc. Grade
- 4.42
- Conc. Grade Unit
- g/t
- Tailings Grade
- 0.17
- Tailings Grade Unit
- g/t
Lab
- Laboratory
- Meeka’s site laboratory
Review
- Needs Review
- No
- Historical
- No
Dates
- Event date
- 2026-11-17T00:00:00.000Z
Reasoning: Successful balanced setting performance.
Positive factors
- High grade product achieved
Evidence · table
“4.42”
Context: 4,088
ore sorterMurchison Gold Project · goldRecovery: 85 %Head Grade: 0.86Head Grade Unit: g/tView all detailsHide details
Identity
- Project
- Murchison Gold Project
- Commodity
- gold
- Region
- australia_wa
- Reported Region
- Western Australia
- Ticker
- MEK
Test Work
- Program Status
- optimization
- Test Type
- ore sorter
- Processing Route
- ore sorter
- Sample
- Total commissioning period product
Recovery
- Recovery
- 85 %
- Head Grade
- 0.86
- Head Grade Unit
- g/t
- Conc. Grade
- 4.39
- Conc. Grade Unit
- g/t
- Tailings Grade
- 0.18
- Tailings Grade Unit
- g/t
Lab
- Laboratory
- Meeka’s site laboratory
Review
- Needs Review
- No
- Historical
- No
Dates
- Event date
- 2026-11-17T00:00:00.000Z
Reasoning: Overall commissioning results show significant grade enhancement.
Positive factors
- 5x grade increase
- 80-90% gold recovery
Evidence · table
“4.39”
Context: 5,412
How Atlas produces this analysis
Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.