# CAV: Kookynie Gold Project Bankable Feasibility Study

Canonical Atlas analysis: https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a

Original source: https://www.asx.com.au/asx/v2/statistics/displayAnnouncement.do?display=pdf&idsId=03156734

Publisher: asx

Original announcement: 2026-10-25T21:23:00.000Z

Analysis by Minestarters Atlas

Atlas analysis published: 2026-10-25T22:31:26.675Z

Atlas analysis updated: 2026-10-25T22:31:26.675Z

- Company: Carnavale Resources Ltd

- Ticker: CAV

- Exchange: ASX

- Region: Western Australia

- Primary commodity: Unavailable

- Secondary commodities: None reported

- Document categories: Other, Resource update, Metallurgy

- Extracted: 2026-10-25 22:30:33 UTC

Narrative sentiment: 0.90 · Bullish

## Minestarters Atlas summary

Carnavale Resources announced positive results from a Bankable Feasibility Study \(BFS\) for its Kookynie Gold Project in Western Australia, outlining a financially viable open-pit development. The BFS reports an undiscounted pre-tax free cash flow of A$104 million, an NPV8 of A$87 million, and an IRR of 417% at a base case gold price of A$6,000/oz, supported by a maiden open pit reserve of 35.6 koz at 5.0 g/t gold. Metallurgical testwork confirmed high gold recoveries \(98-99%\) for a conventional CIL process, and environmental permits have been submitted, advancing the project towards a Final Investment Decision.

Reasoning: The Bankable Feasibility Study demonstrates robust economics for the Kookynie Gold Project's open pit development, including a maiden Ore Reserve, high gold recoveries, and strong financial returns, significantly de-risking the project and positioning it for a Final Investment Decision.

- Positive factor: Strong financial metrics \(NPV, IRR, free cashflow\)

- Positive factor: Maiden open pit reserve declared

- Positive factor: High metallurgical recoveries

- Positive factor: Low capital requirement

- Positive factor: Short payback period

- Positive factor: JORC 2012 compliant

- Positive factor: Environmental permits submitted

- Positive factor: Category upgrade from Indicated to Measured resources

- Negative factor: Reliance on third-party processing \(OPA/TMA\) which is not yet executed

- Negative factor: Funding still needs to be secured

- Negative factor: Underground resource is unchanged and still at Scoping Study level

- Negative factor: Inferred resources included in overall MRE

Low confidence — this extraction should be reviewed alongside the original source.

Facts used in scoring: 20

## Classification and evidence

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: The document is titled 'Kookynie Gold Project Bankable Feasibility Study' and details the development of initial open-pit development.

Evidence · text

> Kookynie Gold Project Bankable Feasibility Study

**Low Capital Intensity**

Polarity: positive

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The BFS highlights a 'low capex' project with a capital requirement of A$24 million.

Evidence · text

> low capex

**Short Payback Period**

Polarity: positive

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The project is projected to have a payback period of 10 months.

Evidence · text

> Payback Month 10

**High IRR**

Polarity: positive

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The BFS reports an Internal Rate of Return \(IRR\) of 417%.

Evidence · text

> IRR of 417%

**High NPV**

Polarity: positive

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The BFS reports an NPV8 of A$87 million.

Evidence · text

> NPV8 A$87 million

**Funding Required**

Polarity: negative

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The document states that securing project funding is a key next step.

Evidence · text

> Securing project funding.

**Third Party Processing**

Polarity: neutral

Story-specific tag

Definition: No canonical definition is currently available.

Why it applies: The KGP is modelled to operate as a contract mining operation with an Ore Purchase Agreement, relying on third-party processing.

Evidence · text

> KGP modelled to operate as a contract mining operation with Ore Purchase Agreement.

**Maiden Resource**

Polarity: neutral

Definition: First formal MRE for the project — establishes baseline but typically exploration-stage with high Inferred component.

Why it applies: The document refers to a 'Maiden open pit reserve' for the KGP.

Evidence · text

> Maiden open pit reserve

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: The MRE and Ore Reserves are reported in accordance with JORC Code 2012 Edition.

Evidence · text

> JORC Code 2012 Edition \(JORC 2012\)

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: Michael Job \(Cube Consulting\) is named as the Competent Person for Mineral Resources and Mitchell Rohr \(Cube Consulting\) for Ore Reserves.

Evidence · text

> Mr Michael Job, who is a Fellow of the Australasian Institute of Mining and Metallurgy \(FAusIMM\). Mr Job is an independent consultant employed by Cube Consulting.

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: The MRE includes a Measured category for the open pit portion of the lodes.

Evidence · table

> Measured

Context: Measured

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: The MRE includes an Indicated category for both open pit and underground portions of the lodes.

Evidence · table

> Indicated

Context: Indicated

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: The MRE includes an Inferred category for both open pit and underground portions of the lodes.

Evidence · table

> Inferred

Context: Inferred

**Category Upgrade**

Polarity: positive

Definition: Resource confidence improved — Inferred upgraded to Indicated, or Indicated to Measured. De-risking signal.

Why it applies: Infill drilling upgraded Indicated Resources to Measured Resources within the proposed pit shells.

Evidence · text

> upgraded Indicated Resources to Measured Resources

**High Recovery**

Polarity: positive

Definition: Recovery at or above the exceptional band for the commodity and processing route.

Why it applies: Metallurgical testwork demonstrated gold recoveries of 98% for oxide and transitional ore, and 99% for fresh ore.

Evidence · text

> gold recoveries of 98% for oxide and transitional ore, and 99% for fresh ore

**Free Milling**

Polarity: positive

Definition: Simple, clean ore amenable to standard processing without oxidation.

Why it applies: Testwork results indicated no issues with preg-robbing, refractory mineralisation, or deleterious elements.

Evidence · text

> no evidence of preg-robbing in the testwork, hence a CIP or CIL configuration would be equally suitable.

**Multi-Domain Tested**

Polarity: positive

Definition: Variability across ore domains \(oxide, transition, fresh\) has been addressed.

Why it applies: Metallurgical testwork was conducted on three mineralogical domains: oxide, transition, and fresh.

Evidence · text

> three mineralogical domains; oxide, transition and fresh

**Mill Route**

Polarity: neutral

Definition: Processing via mill or concentrator \(CIL, CIP, tank leach, flotation\).

Why it applies: The proposed processing route is a conventional CIL gold processing plant.

Evidence · text

> conventional CIL gold processing plant

**Bench Scale Only**

Polarity: negative

Definition: Only preliminary bench tests completed — no locked-cycle or pilot work.

Why it applies: Gravity gold recoveries were tested using a 'laboratory scale Knelson concentrator', indicating bench-scale testwork.

Evidence · text

> laboratory scale Knelson concentrator

**Gravity Route**

Polarity: neutral

Definition: Gravity separation forms a material part of the flowsheet.

Why it applies: the document describes a gravity route \("gravity"\)

**Single Domain Only**

Polarity: negative

Definition: Testing limited to one composite or domain — representativeness not established.

Why it applies: only one composite was tested

## Extracted facts

Stored fact records: 19. Some facts used in scoring do not have a stored record.

## Resource Estimates (18)

### proven

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-1)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: reserve
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Mitchell Rohr
- Resource group id: resource:170cb438744c1e71dd2b
- Deposit or zone: Swiftsure Open Pit
- Mining method: combined

#### Resource Data

- Category: proven
- Tonnes: 131800
- Grade: 5.2
- Grade Unit: g/t
- Contained Metal: 22100
- Contained Unit: oz
- Cutoff Grade: 0.7
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-09-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The maiden Proved Ore Reserve for Swiftsure Open Pit is a significant de-risking milestone, demonstrating high confidence in a substantial, high-grade portion of the deposit.

- Positive factor: Maiden reserve

- Positive factor: High grade

- Positive factor: Proved category

Evidence · table

> 131.8

Context: Proved

#### Tags used in scoring

**Proven Reserve**

Polarity: positive

Definition: Measured Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "proven"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### probable

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-2)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: reserve
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Mitchell Rohr
- Resource group id: resource:0d4aafa0e0746391e7ae
- Deposit or zone: Swiftsure Open Pit
- Mining method: combined

#### Resource Data

- Category: probable
- Tonnes: 35000
- Grade: 7.9
- Grade Unit: g/t
- Contained Metal: 8900
- Contained Unit: oz
- Cutoff Grade: 0.7
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-09-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The maiden Probable Ore Reserve for Swiftsure Open Pit adds to the economic viability, with a high-grade component.

- Positive factor: Maiden reserve

- Positive factor: High grade

Evidence · table

> 35.0

Context: Probable

#### Tags used in scoring

**Probable Reserve**

Polarity: positive

Definition: Indicated Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "probable"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### proven

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-3)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: reserve
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Mitchell Rohr
- Resource group id: resource:451513ed902aa673e745
- Deposit or zone: Tiptoe Open Pit
- Mining method: combined

#### Resource Data

- Category: proven
- Tonnes: 42800
- Grade: 2.2
- Grade Unit: g/t
- Contained Metal: 3000
- Contained Unit: oz
- Cutoff Grade: 0.7
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-09-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The maiden Proved Ore Reserve for Tiptoe Open Pit contributes to the overall project reserve, providing additional economic material.

- Positive factor: Maiden reserve

- Positive factor: Proved category

Evidence · table

> 42.8

Context: Proved

#### Tags used in scoring

**Proven Reserve**

Polarity: positive

Definition: Measured Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "proven"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### probable

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-4)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: reserve
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Mitchell Rohr
- Resource group id: resource:a9b615f87a6ddc4716e1
- Deposit or zone: Tiptoe Open Pit
- Mining method: combined

#### Resource Data

- Category: probable
- Tonnes: 10400
- Grade: 4.5
- Grade Unit: g/t
- Contained Metal: 1500
- Contained Unit: oz
- Cutoff Grade: 0.7
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-09-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The maiden Probable Ore Reserve for Tiptoe Open Pit adds to the overall project reserve, albeit with a smaller contribution.

- Positive factor: Maiden reserve

Evidence · table

> 10.4

Context: Probable

#### Tags used in scoring

**Probable Reserve**

Polarity: positive

Definition: Indicated Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "probable"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### measured

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-5)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Michael Job
- Resource group id: resource:7e0510690a4b89705a5b
- Deposit or zone: Swiftsure and Tiptoe lodes
- Mining method: combined

#### Resource Data

- Category: measured
- Tonnes: 182000
- Grade: 5.1
- Grade Unit: g/t
- Contained Metal: 30000
- Contained Unit: oz
- Cutoff Grade: 0.8
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-05-31

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The Measured resource for the open pit portion of Swiftsure and Tiptoe lodes indicates high geological confidence and contributes significantly to the project's economic viability.

- Positive factor: High confidence Measured resource

- Positive factor: High grade

Evidence · table

> 182

Context: Measured

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### indicated

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-6)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Michael Job
- Resource group id: resource:c5d522b0c9c5449e27eb
- Deposit or zone: Swiftsure and Tiptoe lodes
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 101000
- Grade: 3.6
- Grade Unit: g/t
- Contained Metal: 12000
- Contained Unit: oz
- Cutoff Grade: 0.8
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-05-31

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The Indicated resource for the open pit portion provides reasonable geological confidence for future planning.

- Positive factor: Indicated resource

Evidence · table

> 101

Context: Indicated

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### inferred

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-7)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Michael Job
- Resource group id: resource:73bf3385db0f61caeaa6
- Deposit or zone: Swiftsure and Tiptoe lodes
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 126000
- Grade: 2.5
- Grade Unit: g/t
- Contained Metal: 10000
- Contained Unit: oz
- Cutoff Grade: 0.8
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-05-31

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The Inferred resource for the open pit portion has lower geological confidence and cannot be used for economic studies without further drilling.

- Negative factor: Inferred category

- Negative factor: Lower confidence

Evidence · table

> 126

Context: Inferred

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### indicated

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-8)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Michael Job
- Resource group id: resource:30f058de0c86c0804045
- Deposit or zone: Swiftsure and Tiptoe lodes
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 177000
- Grade: 6.7
- Grade Unit: g/t
- Contained Metal: 38000
- Contained Unit: oz
- Cutoff Grade: 1.5
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-05-31

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The Indicated resource for the underground portion of Swiftsure and Tiptoe lodes shows high-grade potential for future development.

- Positive factor: High grade

- Positive factor: Indicated resource

Evidence · table

> 177

Context: Indicated

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### inferred

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-9)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- QP Signed: Yes
- Qualified person names: Michael Job
- Resource group id: resource:b969ccf43efe186a2612
- Deposit or zone: Swiftsure and Tiptoe lodes
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 269000
- Grade: 3.5
- Grade Unit: g/t
- Contained Metal: 30000
- Contained Unit: oz
- Cutoff Grade: 1.5
- Cutoff Unit: g/t

#### Prior Estimate

- Resource Date: 2026-05-31

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: The Inferred resource for the underground portion has lower geological confidence and requires further drilling to upgrade.

- Negative factor: Inferred category

- Negative factor: Lower confidence

Evidence · table

> 269

Context: Inferred

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

### measured

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-11)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:a421a44c2033ca8be4b4
- Mining method: combined

#### Resource Data

- Category: measured
- Tonnes: 182196
- Grade: 5.06
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 5.06

Context: 182,196

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### indicated

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-12)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:faeed8b6d7c65cf64156
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 101123
- Grade: 2.59
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.59

Context: 101,123

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### inferred

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-13)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:0d474c358e2f8639d06c
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 125661
- Grade: 2.43
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.43

Context: 125,661

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### measured

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-14)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:0bd7967e601edf0484a0
- Mining method: combined

#### Resource Data

- Category: measured
- Tonnes: 9
- Grade: 2.7
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.70

Context: 9

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### indicated

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-15)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:d6fe9d56a7dc64d396f8
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 177265
- Grade: 2.7
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.70

Context: 177,265

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### inferred

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-16)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:854c455f09325205874e
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 268731
- Grade: 2.7
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.70

Context: 268,731

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### measured

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-17)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:226a7613354e1c9f38f6
- Mining method: combined

#### Resource Data

- Category: measured
- Tonnes: 182205
- Grade: 2.42
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.42

Context: 182,205

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### indicated

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-18)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:ee0cadf314053ae8b8d8
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 278388
- Grade: 2.66
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.66

Context: 278,388

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

### inferred

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-resource-facts-19)

MRE for Kookynie · gold

#### Identity

- Project: MRE for Kookynie
- Commodity: gold
- Ticker: CAV

#### Resource scope

- Estimate type: resource
- Reporting standards: jorc
- Resource group id: resource:3a7b295bda7c73e0d290
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 399193
- Grade: 2.64
- Grade Unit: g/t

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Expanded from multi-commodity resource table for completeness.

- Negative factor: Fact expanded from resource table columns \(model omitted this commodity\).

Evidence · table

> 2.64

Context: 399,193

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: reporting\_standards includes jorc

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

## Metallurgical Results (1)

### cyanidation leach

[Link to this fact](https://atlas-aws.minestarters.com/news/cav-kookynie-gold-project-bankable-feasibility-study--b1889ab1-3b0c-4ad2-9937-198680211b3a#fact-metallurgical-facts-10)

Kookynie Gold Project · gold

#### Identity

- Project: Kookynie Gold Project
- Commodity: gold
- Region: australia\_wa
- Reported Region: Western Australia
- Ticker: CAV

#### Test Work

- Test Type: cyanidation leach
- Processing Route: Cyanidation Leach
- Sample: Fresh Master Composite
- Grind P80: 130 µm

#### Recovery

- Recovery: 97.8 %
- Recovery Basis: actual\_test

#### Reagents

- Cyanide: 0.2 kg/t
- Lime: 1.73 kg/t

#### Lab

- Laboratory: IMO Metallurgy
- Consultant: Strategic Metallurgy

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-10-25T00:00:00.000Z

Reasoning: Excellent gold recovery from fresh composite at a coarser grind, with very low cyanide consumption, further confirming robust processing characteristics at bench scale.

- Positive factor: High recovery

- Positive factor: Very low cyanide consumption

- Negative factor: Bench scale only

Evidence · table

> 97.8

Context: P80 130μm

#### Tags used in scoring

**High Recovery**

Polarity: positive

Definition: Recovery at or above the exceptional band for the commodity and processing route.

Why it applies: 97.8% is at or above the exceptional band \(95%\)

## How Atlas produces this analysis

Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.